CI Workflows & Failure Behavior
A complete, minimal workflow
This is a real workflow, taken directly from
ProtocolCanary-Action’s examples/protocol-28.yml
— checking a project against the real Protocol 28 fixture pack, against a
live Testnet RPC endpoint:
name: Stellar Compatibility (Protocol 28)
on:
pull_request:
permissions:
contents: read
jobs:
compatibility:
runs-on: ubuntu-latest
steps:
- name: Checkout project
uses: actions/checkout@v4
- name: Checkout Protocol 28 fixtures
uses: actions/checkout@v4
with:
repository: StellarCanary/ProtocolCanary-Fixtures
path: canary-fixtures
- name: Stellar Protocol Canary
uses: StellarCanary/ProtocolCanary-Action@v1
with:
protocol: "28"
fixtures-dir: canary-fixtures/protocol-28
network: testnet
rpc-url: https://soroban-testnet.stellar.org
permissions: contents: read is sufficient — the Action does not need
write access to your repository to check compatibility. A project with no
Soroban contracts, for example, can set [tests] soroban = false in its
own .stellar-canary.toml without this workflow needing to change.
Using the Action’s outputs
- name: Stellar Protocol Canary
id: canary
uses: StellarCanary/ProtocolCanary-Action@v1
with:
protocol: "28"
upload-report: "true"
- name: Show result
if: always()
run: |
echo "status: ${{ steps.canary.outputs.status }}"
echo "passed: ${{ steps.canary.outputs.passed }}"
echo "failures: ${{ steps.canary.outputs.failures }}"
(From examples/pull-request.yml.)
Two different kinds of “red”
The Action distinguishes a compatibility failure from an execution failure — they are not the same thing, and it never conflates them:
| Compatibility failure | Execution failure | |
|---|---|---|
| Meaning | Canary ran successfully and found a real incompatibility | Canary could not be installed, could not run, timed out, or produced output that could not be parsed |
status output | fail (or warning/error) | execution-failed |
| Job summary | A per-surface table naming the specific failing test IDs | “Protocol Canary could not be executed” with the actual diagnostic — never a fabricated compatibility message |
A third, separate case — the job summary itself failing to publish — is reported as “Failed to publish Canary summary,” distinct from both.
What a compatibility failure looks like
When a fixture’s assertion genuinely fails, the underlying CLI exits 1
(see Exit Codes), and:
- The job fails — the workflow step reports non-zero.
- The job summary shows the per-surface pass/fail table with the
specific failing
testId(s). - A GitHub annotation is created pointing at the failing fixture (when
annotations: true, the default). - The artifact (
stellar-protocol-canary-report, whenupload-report: true) still uploads — a compatibility failure is a real result, not an upload problem, so the report is preserved for inspection either way.
This has been verified end-to-end against the real, published @v1
Action: a deliberate FAIL run produced a failed job, an annotation naming
the exact failing fixture, status: fail, and the JSON artifact matching
the documented schema — the same pipeline as a PASS run, just with a
different, honestly reported result.
Network vs. compatibility failures
A failure to reach the configured RPC endpoint is not a compatibility
failure — it is an execution problem. status is error (not fail),
the affected fixtures report "status": "error" with a transport-error
message, and any offline (XDR) fixtures in the same run are unaffected and
still report their real pass/fail result. See
Network Troubleshooting